How to split Splitting Projects into Stages with SOLIDWORKS Manage
Article by Joe Medeiros, CSWE updated January 7, 2019
Article
If there is a period of time where no work is being done on a SOLIDWORKS Manage Project, the Project can be Split, so that time is not included in the percentage completion of Project.
To do this, after creating or editing a Project, select the Planning tab.

Planning Tab of Project
Right-click a Stage and select Split Stage.

Split Stage
Click on Add to create the Split

Add Split
Define the Position of the Split, relative to the Project timeline, and the Length, in number of days, assigned to the Split. An example can be toggled, to help under how the Position and Time are evaluated. A calculator is available from a pull-down, to calculate both the Position and Length

Create Split
A Split can also be removed

Remove Split